Home � GRID INTEGRATION � Grid connection requirements � Grid codes and essential requirements for wind power plants |
The arrangement of the technical requirements within grid codes and related documents varies between electricity systems. However, for simplicity the typical requirements for generators can be grouped as follows:
- Tolerance - the range of conditions on the electricity system for which wind farms must continue to operate;
- Control of reactive power - often this includes requirements to contribute to voltage control on the network;
- Control of active power;
- Protective devices; and
- Power quality.
It is important to note that these requirements are often specified at the Point of Common Coupling (PCC) between the wind farm and the electricity network. In this case, the requirements are placed at wind farm level, and wind turbines may be adapted to meet these requirements. Often, wind turbine manufacturers specify the performance of their wind turbines, rather than for the entire wind farm.
It is also possible for some requirements to be met by providing additional equipment, separate from the turbines; this is indicated, where relevant, in the following discussion.
Acknowledgements | Sitemap | Partners | Disclaimer | Contact | ||
coordinated by |
supported by |
The sole responsibility for the content of this webpage lies with the authors. It does not necessarily reflect the opinion of the European Communities. The European Commission is not responsible for any use that maybe made of the information contained therein. |
ArtWhere offers you services in Content Management System, CMS, Design, Web positioning and Hosting . © ArtWhere s.a.Neo-CMS ver 1.703 © ArtWhere s.a. | ||